T.G Ascent

T.G Ascent

January Updates

C Block
  • 1. Footings concrete completed.
  • 2. Pedestal concrete completed.
  • 3. Back filling in progress up to plinth bottom.
  • 4. East side and North side retaining wall concreting completed.
  • 5. Lift shear wall concreting completed.
D Block
  • 1. Footings concrete completed.
  • 2. Pedestal concrete completed.
  • 3. Back filling in progress.
  • 4. Lift reinforcement work in progress.
A Block
  • 1. Footings PCC and Column marking completed.
  • 2. North and South side retaining wall PCC completed.
  • 3. Footings column reinforcement work has started.