T.G Ascent

T.G Ascent

September 2018 Updates

A – BLOCK
  • 1. Ground floor shuttering work in progress.
B – BLOCK
  • 1. Basement slab shuttering work completed.
  • 2. Beam reinforcement work is completed.
  • 3. Slab reinforcement work in progress.
C – BLOCK
  • 1. First floor slab shuttering work completed.
  • 2. Basement drain block work completed.
D- BLOCK
  • 1. Ground floor slab concreting completed.
  • 2. Ground floor to first floor column casting completed.
  • 3. Basement drain block work completed.
PODIUM
  • 1. Plinth beam casting in progress.

August 2018 Updates

A – BLOCK
  • 1. Basement to ground floor column casting completed.
  • 2. Ground floor slab shuttering work in progress.
B – BLOCK
  • 1. Basement slab shuttering work in progress.
C – BLOCK
  • 1. Ground floor slab concreting completed.
  • 2.Ground floor to first floor column casting completed.
  • 3.Basement drain PCC work completed.
  • 4.First floor slab shuttering work in progress.
D- BLOCK
  • 1. Ground floor slab shuttering work completed.
  • 2. Ground floor slab reinforcement work in progress.
  • 3. Basement drain PCC work completed.
PODIUM
  • 1. Podium Consolidation work in progress.
  • 2. Podium PCC for plinth beam in progress.

July 2018 Updates

A – BLOCK
  • 1. Basement slab concrete completed.
  • 2. Stilt floor column marking in progress.
B – BLOCK
  • 1. Basement floor column casting completed.
  • 2. South side retaining wall completed.
  • 3. West side retaining wall reinforcement and shuttering work in progress.
C – BLOCK
  • 1. Stilt floor slab shuttering completed.
  • 2. Stilt floor slab beam reinforcement completed.
  • 3. Bottom reinforcement work in progress.
D- BLOCK
  • 1. Stilt floor slab shuttering work in progress.
PODIUM
  • 1. Column footing completed.
  • 2. Back filling in progress.

June 2018 Updates

A – BLOCK
  • 1. Basement roof slab shuttering in progress.
  • 2. Retaining wall east and south side completed.
  • 3. Column casting completed.
B – BLOCK
  • 1.Footing pedestal and back filling completed.
  • 2.Retaining wall south side and west side second lift completed.
  • 3.Retaining wall south side third lift in progress.
  • 4.Back filling completed.
  • 5.Plinth beam reinforcement in progress.
C – BLOCK
  • 1.Ground floor to first floor column casting completed.
  • 2.Ground floor roof slab shuttering work in progress.
D- BLOCK
  • 1.Basement roof concrete completed.
  • 2.Ground floor to first floor column reinforcement in progress.
PODIUM
  • 1.Column footing in progress. 50% completed.
  • 2.Back filling in progress.

May 2018 Updates

A – BLOCK
  • 1. PCC work completed.
  • 2. Column casting work in progress.
  • 3. Retaining wall east side and south side third lift in progress.
B – BLOCK
  • 1.Footing pedestal and back filling in progress.
  • 2.Retaining wall south side and west side second lift in progress.
C – BLOCK
  • 1.Basement roof slab completed.
  • 2.Basement floor to ground floor column casting in progress.
  • 3.Reinforcement work for column in progress.
D- BLOCK
  • 1.Basement roof shuttering work in progress.
  • 2.North side and west side retaining wall casting completed.
  • 3.Column concrete work completed.
PODIUM
  • 1.Footing casting work in progress.

April 2018 Updates

A – BLOCK
  • 1. Plinth beam concrete casting completed.
  • 2. Back filling and PCC work in progress.
B – BLOCK
  • 1.South side retaining wall second lift completed.
  • 2.Footing concrete in progress.
  • 3.Pedestal concrete in progress.
C – BLOCK
  • 1.Basement floor shuttering completed.
  • 2.Slab reinforcement work in progress.
D- BLOCK
  • 1.Plinth beam back filling completed.
  • 2.PCC work completed.
  • 3.North side retaining wall third lift shuttering work completed.
  • 4.Column concrete work in progress.

March 2018 Updates

A – BLOCK
  • 1. Footing concrete completed.
  • 2. Pedestal concrete completed.
  • 3. Footing Back filling in progress.
B – BLOCK
  • 1. Footing concrete work in progress.
C – BLOCK
  • 1. Column casting up to basement floor completed.
  • 2. PCC and plinth beam concrete casting completed.
  • 3. Beam bottom shuttering work in progress.
D- BLOCK
  • 1. Plinth beam concrete completed.
  • 2. PCC work in progress.
  • 3. Column reinforcement lapping up to basement floor slab in progress.

February 2018 Updates

A – BLOCK
  • 1. Footing and pedestal concrete completed.
  • 2. Back filling in progress.
  • 3. Retaining wall raft footing completed.
  • 4. East facing retaining wall 1st lift completed.
B – BLOCK
  • 1. Retaining wall raft footing completed.
  • 2. West side retaining wall PCC work completed.
  • 3. Excavation and PCC work in progress.
  • 4. Footing concrete in progress.
C – BLOCK
  • 1. Plinth beam completed.
  • 2. Plinth beam back filling completed.
  • 3. Column lapping work upto slab level in progress.
  • 4. Retaining wall 1st lift concrete completed.
D- BLOCK
  • 1. Back filling completed.
  • 2. Retaining wall 1st lift concrete completed.
GENERAL
  • Erection of Batching plant work in progress.
  • Block work for operator’s room, sump & hopper installation in progress.

January 2018 Updates

C Block
  • 1. Footings concrete completed.
  • 2. Pedestal concrete completed.
  • 3. Back filling in progress up to plinth bottom.
  • 4. East side and North side retaining wall concreting completed.
  • 5. Lift shear wall concreting completed.
D Block
  • 1. Footings concrete completed.
  • 2. Pedestal concrete completed.
  • 3. Back filling in progress.
  • 4. Lift reinforcement work in progress.
A Block
  • 1. Footings PCC and Column marking completed.
  • 2. North and South side retaining wall PCC completed.
  • 3. Footings column reinforcement work has started.