T.G Epitome

T.G EPITOME

March 2018 Updates

  • 1. Basement completed.
  • 2. Children's play area completed.
  • 3. Basement entrance ramp completed.
  • 4. STP - completed.
  • 5. B block common area granite work completed.
  • 6. B block staircase granite completed.
  • 7. Common area lighting completed.
  • 8. B block internal painting work in progress.
  • 9. B Block external painting in progress.

January Updates

A – Block
  • 1. 20flats ready for Handover.
  • 2. Passenger lifts – completed.
  • 3. Electrical work completed on all the floors.
  • 4. External paint – 1 Coat completed.
  • 5. Plumbing work completed on all the floors.
  • 6. Door fitting work completed.
  • 7. UPVC sliding doors and windows installation work is in progress on the ground floor.
  • 8. CP & sanitary fittings work in progress.
B – Block:
  • 1. Flooring tile work completed on all the floors.
  • 2. External primer work is completed on all the sides.
  • 3. One coat putty work completed in all the flats.
  • 4.External plastering work completed.
  • 5.Staircase railing work is completed.
  • 6.Second coat putty and primer work in progress on the first floor.
  • 7.Common area granite work initiated at the First floor.
  • 8.UPVC sliding doors and windows work initiated.
  • 9.Door fitting work in progress.
  • 10.Plumbing work in progress.
Amenities:
  • 1. Tiling in the Multipurpose hall and gym completed.
  • 2. Swimming pool water proofing completed.
  • 3. Children’s play areamarking completed.
  • 4. Compound external plastering work completed on 3 sides.